Posted by on June 23, 2007, 4:14 pm
Our house (in Wisconsin) is finished. According to the bid we
accepted, we owe one final payment of $60,000 ($53,000 plus $7,000 to
account for change requests during the construction process) to our
general contractor. Now, right at the end, he suddenly says we owe
him $73,000. He says if we don't pay it, he's going to sue us. Can
he doe this to us? Here are his reasons:
1. His estimates were inaccurate, and some of his sources for
material and labor ended up charging him more than he expected.
2. We bothered him with a lot of changes and supervision.
3. Our house is worth a lot more than we're paying him.
4. The house too him longer to build than he expected, and so he had
to pay a lot more for labor than he expected.
Here are my answers to him on each of the four issues:
1. Regarding his costs exceeding his estimates... We had an oral
agreement in the beginning that once we agreed on a project and
accepted his bid that the bid would not change--up or down. If we
made changes (we did make minor changes), we would be responsible for
our changes. If market prices on materials were to fall, we agreed
that he would enjoy the savings, but if prices went up, he would
suffer the extra charges. He called this "locking in," and that is
one of the main reasons we went with this contractor. On the detailed
written bid he provided us, and which we subsequently accepted, he
even wrote his "lock in" promise at the bottom--a few sentences.
Other than these written documents and or oral contract, we have no
official contract with him.
2. Regarding his claim that we bothered him with changes and
supervision... He never once discouraged this or said that there
would be extra charges, other than the cost of the actual changes,
which we are agreeing to pay--$7,000 for specific changes bringing the
total due up to $60,000. But he wants $73,000! As for his claim that
we bothered him with a lot of supervision and faxed notes... He never
discouraged this, and the only reason for the close supervision and
notes was because his crew made a *LOT* of mistakes that had to be
corrected. The work was very substandard. All of this is
documented. I think our supervision and notes actually helped them
get through the job and finish it the way we intended it to be
finished. They were very unprofessional.
3. Regarding his claim that our house is worth a lot so we should pay
a lot... Why should we be penalized because we came up with a great
design and made wise choices for materials and features? He offered
us a bid in the beginning, and we accepted. Now, because the house is
very attractive (mostly because of the land and neighborhood), why
should he be entitled to more money? His complaint is that he didn't
charge enough initially, and now he's going to lose at least $30,0000,
and that we should have to pay for his losses because our house only
cost us $290,000 and it's worth about $450,000. First of all, I think
it's worth $350,000 at the most, and even if it was worth $450,000,
that would be like a mechanic complaining because he sold us an engine
for $5,000 and we put it in a car we bought for $7,000, and now that
car is now worth $20,000--too bad, right?
4. Regarding his claim that the house took longer to build than
expected... Isn't that his fault? The reason it took longer is
because his crew are slow, lazy, and inept. They made a lot of
mistakes that they had to fix. Likewise, everything based on time
cost about double--the dumpster, the crane, etc. In fact, this
actually cost us money, because we paid four months longer than
expected on our construction loan without being able to live in the
house--shouldn't we be entitled for some compensation for that?
This is all causing us a lot of stress, and it sounds like it's going
to cost us a lot of legal fees now, too. I feel violated. What can
we do? Please advise. Any helpful information would be greatly
appreciated.
Thanks,
Unhappy
|
|
Posted by Tony on June 23, 2007, 5:05 pm
> This is all causing us a lot of stress, and it sounds like it's going
> to cost us a lot of legal fees now, too. I feel violated. What can
> we do? Please advise. Any helpful information would be greatly
> appreciated.
Just pay what you agreed to pay, he'll go away.
he's not going to file a lien.
when are you going to pay him?
will it be in cash? what address will you be delivering this 60,000.00 to?
time and date too
thanks
Posted Via Usenet.com Premium Usenet Newsgroup Services
----------------------------------------------------------
** SPEED ** RETENTION ** COMPLETION ** ANONYMITY **
----------------------------------------------------------
http://www.usenet.com
|
|
Posted by on June 23, 2007, 5:11 pm
And what if he doesn't go away? What if he sues us like he said he's
going to? What if he's stupid and he doesn't realize we're
right? ...thousands of dollars in legal fees later... Is there any
way he could win? Wouldn't it cost more than the difference that
we're arguing over in legal fees and court costs? Who would have to
pay those fees? Could we make him pay our attorney fees if we win?
So many questions, so little time... So many unethical contractors,
not enough bullets...
I must say, our excavating/landscaping contractor was brilliant and
fair, and our concrete and plumbing contractors did perfect work for a
very good price. Everybody else was shite!
- Unhappy
> Just pay what you agreed to pay, he'll go away.
> he's not going to file a lien.
>
> when are you going to pay him?
> will it be in cash? what address will you be delivering this 60,000.00 to?
> time and date too
>
> thanks
>
> Posted Via Usenet.com Premium Usenet Newsgroup Services
> ----------------------------------------------------------
> ** SPEED ** RETENTION ** COMPLETION ** ANONYMITY **
> ----------------------------------------------------------
> http://www.usenet.com
|
|
Posted by Tony on June 23, 2007, 5:37 pm
> And what if he doesn't go away? What if he sues us like he said he's
> going to? What if he's stupid and he doesn't realize we're
> right? ...thousands of dollars in legal fees later... Is there any
> way he could win?
no way, if he ever stood a chance, he hung himself with your material price
warranty
the judge would say, "mr contractor, consider 13,000 a cheap education on
how to bid a job"
>Wouldn't it cost more than the difference that
> we're arguing over in legal fees and court costs? Who would have to
> pay those fees? Could we make him pay our attorney fees if we win?
> So many questions, so little time... So many unethical contractors,
> not enough bullets...
If you start talking settlement with the contractor, he's going to get the
big head and think his request is ok
it's not ok
he should validate this, he should admit to underpricing..
tell him show you where any material cost 13,000 more than original bid
reflects
you're right! it's not your problem if he can't manage people
the judge is going to laugh him out of the court room
Posted Via Usenet.com Premium Usenet Newsgroup Services
----------------------------------------------------------
** SPEED ** RETENTION ** COMPLETION ** ANONYMITY **
----------------------------------------------------------
http://www.usenet.com
|
|
Posted by Tony on June 23, 2007, 7:49 pm
> And what if he doesn't go away?
why haven't you paid him the 60,000?
this much you two agree on
Posted Via Usenet.com Premium Usenet Newsgroup Services
----------------------------------------------------------
** SPEED ** RETENTION ** COMPLETION ** ANONYMITY **
----------------------------------------------------------
http://www.usenet.com
|
Page 1 of 7 1 2 3 > last >>
| Similar Threads | Posted | | price burst view 3D | June 8, 2007, 3:34 am |
| Book (general reading) Recommendation Question | August 5, 2008, 12:21 pm |
| Sunroom Kit or Sunroom Contractor? | June 20, 2007, 11:34 pm |
| Q: "hinge house"? | January 30, 2007, 3:53 pm |
| New photos of our house | February 20, 2007, 1:45 pm |
| Recordings of This Old House? | April 21, 2007, 5:03 am |
| Newspaper "House" | March 8, 2008, 8:11 pm |
| House Hunters | May 19, 2008, 11:58 pm |
| Updates on the construction of our "new old house" | January 21, 2007, 10:09 am |
| House Plan Ideas | August 15, 2007, 3:21 pm |
|
|