Home Page link

Concrete Questions for Garage Construction.....

Building Construction - Building Construction Industry Discussions. 

Bookmark this page:  YahooMyWeb Yahoo!  Google Google  Windows Live Favorites Windows Live  del.icio.us del.icio.us  digg digg  Add to Netscape Netscape
Subject Author Date
Concrete Questions for Garage Construction..... Solomon_Man 05-30-2007
If you were  Registered and logged in, you could reply and use other advanced thread options
Posted by Solomon_Man on May 30, 2007, 12:07 pm
All,
I am working on adding two garages on my property. The larger is a
24X32 and the smaller one is 14X20. My father was in construction and
I have done about everything in-home construction, except, major
concrete. I have done sidewalks, patios, etc but nothing major. This
is where my questions originate.

I have read a few books and gotten my permits. I marked out the
location of the new garages and squared them up over last week after
work. Then last weekend, I broke ground with an excavator and a large
bobcat. Knowing that I would be better off (concrete savings) having a
professional dig the actual footer, I hired a friend of a friend to
dig my footer and I operated the bobcat. Things went as expected and
my figures for stone and supplies came out. I am preparing for
inspection and this morning I cleared out the roots from a few trees
that sit in the back 30 feet of my property. I am planning on pouring
the footer then the finished slab.

The one thing that I am concerned about is during the excavation we
ran into two leach fields (at 3 feet down), an old septic leach bed
and a leach bed from an old gray water system (at 2 feet down). I am
positive that these systems are both no longer used and the main tanks
are filled with sand. I know this for certain because I did this and
the new sewer line to the house (120 feet)with my dad when the city
sewer came to our area about 10 years ago. The septic system was
original with the house (50 years old) and was about 200 gallons (very
very small) and the leach field was only 120 feet in a Y. The gray
water system ran the washing machine and dishwasher only and was 110
gallons and had only a 45 feet leach system but had a very large
diameter.

How is something like this normally handled?

I have, so far, crushed and removed them from the footer entirely and
have filled them with foam and packed the ends with dirt and stone
tightly. There was no water in either system as expected.

Are these pipes even a concern at this point?

My next question is concerning the next steps in the concrete process.

My plans, and please correct me if I am wrong, is the following;

1) I will get approval from the city that my footer and stone etc is
good.
I assume they are mostly concerned with depth, width, and straightness
of the footer and the stone is 4 inch or better.
2) I will rebar the footer
3) I will bring in the concrete and pour the footer to the bottom of
the stone. (stone started 4 inches below earth grade)
4) I will then place my forms (2X8s) and make sure everything is of
correct size and square up the forms.
5) I will place my 6X6 10 Gauge wire mesh to the footer
6) I will then have the concrete brought in and will pour and level
out with a Bull float/screeds/maybe even a power trowel.
7) I will then place the garage bolts for the sill board
8) Spray on curing agent

Now, I am considering having the above done after I get approval from
the city inspection. As I have a friend who has a friend that does
this for a living. I have seen his work and I think it looks decent.
So everyone knows, this is very against my grain as I hire very few
things out. My main concern is the man power behind this and the skill
to do the final level/finish but I know getting to this point is a
very big step.

Now what should I expect to pay outside the cost of materials to have
him do this? What is the norm? I have been told he will bring in 4
guys at $250 a day for the actual pour. What should form, rebar and
mesh placement cost me?

I have another option to finish this concrete which is decent as well.
I personally have a long time friend that is in the heavy machine
operating trade (40 + years) and has done a lot of large scale
concrete/masonry in his life. I have seen his work and it is decent.

Any opinions or suggestions?

Sorry for the rambling.

Thanks,
Chris
Solomon_Man


Posted by Solomon_Man on May 30, 2007, 4:52 pm
> All,
> I am working on adding two garages on my property. The larger is a
> 24X32 and the smaller one is 14X20. My father was in construction and
> I have done about everything in-home construction, except, major
> concrete. I have done sidewalks, patios, etc but nothing major. This
> is where my questions originate.
>
> I have read a few books and gotten my permits. I marked out the
> location of the new garages and squared them up over last week after
> work. Then last weekend, I broke ground with an excavator and a large
> bobcat. Knowing that I would be better off (concrete savings) having a
> professional dig the actual footer, I hired a friend of a friend to
> dig my footer and I operated the bobcat. Things went as expected and
> my figures for stone and supplies came out. I am preparing for
> inspection and this morning I cleared out the roots from a few trees
> that sit in the back 30 feet of my property. I am planning on pouring
> the footer then the finished slab.
>
> The one thing that I am concerned about is during the excavation we
> ran into two leach fields (at 3 feet down), an old septic leach bed
> and a leach bed from an old gray water system (at 2 feet down). I am
> positive that these systems are both no longer used and the main tanks
> are filled with sand. I know this for certain because I did this and
> the new sewer line to the house (120 feet)with my dad when the city
> sewer came to our area about 10 years ago. The septic system was
> original with the house (50 years old) and was about 200 gallons (very
> very small) and the leach field was only 120 feet in a Y. The gray
> water system ran the washing machine and dishwasher only and was 110
> gallons and had only a 45 feet leach system but had a very large
> diameter.
>
> How is something like this normally handled?
>
> I have, so far, crushed and removed them from the footer entirely and
> have filled them with foam and packed the ends with dirt and stone
> tightly. There was no water in either system as expected.
>
> Are these pipes even a concern at this point?
>
> My next question is concerning the next steps in the concrete process.
>
> My plans, and please correct me if I am wrong, is the following;
>
> 1) I will get approval from the city that my footer and stone etc is
> good.
> I assume they are mostly concerned with depth, width, and straightness
> of the footer and the stone is 4 inch or better.
> 2) I will rebar the footer
> 3) I will bring in the concrete and pour the footer to the bottom of
> the stone. (stone started 4 inches below earth grade)
> 4) I will then place my forms (2X8s) and make sure everything is of
> correct size and square up the forms.
> 5) I will place my 6X6 10 Gauge wire mesh to the footer
> 6) I will then have the concrete brought in and will pour and level
> out with a Bull float/screeds/maybe even a power trowel.
> 7) I will then place the garage bolts for the sill board
> 8) Spray on curing agent
>
> Now, I am considering having the above done after I get approval from
> the city inspection. As I have a friend who has a friend that does
> this for a living. I have seen his work and I think it looks decent.
> So everyone knows, this is very against my grain as I hire very few
> things out. My main concern is the man power behind this and the skill
> to do the final level/finish but I know getting to this point is a
> very big step.
>
> Now what should I expect to pay outside the cost of materials to have
> him do this? What is the norm? I have been told he will bring in 4
> guys at $250 a day for the actual pour. What should form, rebar and
> mesh placement cost me?
>
> I have another option to finish this concrete which is decent as well.
> I personally have a long time friend that is in the heavy machine
> operating trade (40 + years) and has done a lot of large scale
> concrete/masonry in his life. I have seen his work and it is decent.
>
> Any opinions or suggestions?
>
> Sorry for the rambling.
>
> Thanks,
> Chris
> Solomon_Man

All,
The tile for the leach field for the septic system is a orange
ceramic
- 3 or 4inch (very small) and the gray water system is a 8 inch pipe
that is coming up to the front right corner of the garage. I was able
to use a knife and cut the 8 inch pipe, with a pocket knife, one foot
back completely away from the garage and its footer. The pipe is a
thin black pipe very flexible with what seems to be clothe
surrounding
it. The 8 inch pipe was also at the end of its run and lucky for me
ran till its end in my footer which of course I completely removed.
The 8 inch pipe is not under the garage nor is it, at least in my
opinion, a in the way problem. If the 8 inch is a problem I would
prefer to remove it after the footer is poured as it goes back I am
guessing 20 or so feet to the tank to avoid screwing up my footer
walls and using excess concrete. The ceramic pipe is 3 feet down and
my area soil is thick dark clay. The ceramic is somewhat of a concern
but to remove it would require a complete diagonal cut across my
24X32
garage at three foot. Before I would consider digging it up, I would
look at options of filling it with solid concrete as it would only be
a additional 1/2 yard (max) according to my figures.

Just some more information.


Thanks,
Chris
Solomon_Man


Posted by DanG on May 30, 2007, 7:50 pm
If the old lines crossed the footing, no big deal. If they ran
the same way as the footing, you need to worry about compaction
and dig down to undisturbed soil. An 8 inch pipe you can cut with
a knife sounds huge for gray water, sounds more like an area
drain. Deal with it after you stabilize the area.


My plans, and please correct me if I am wrong, is the following;

1) I will get approval from the city that my footer and stone etc
is good. I assume they are mostly concerned with depth, width,
and straightness of the footer and the stone is 4 inch or better.

What stone? Yes, they will be looking for frost depth. Footing
inspection here would expect the steel in location, tied,
supported, proper distance from dirt, correct laps, and corner
bars. They really don't care if it is straight or over wide -
those are things you need.

2) I will rebar the footer

See above. Code here demands 2 #5 continuous, lapped 32 bar
diameters where necessary, corner bars tied in.

3) I will bring in the concrete and pour the footer to the bottom
of the stone. (stone started 4 inches below earth grade)

The inspector may demand that reinforcing steel tie the slab to
the footing, I would J bolts should extend into the reinforced
footing zone. I guess you are talking about a gravel sub base
under the slab. You will want finish floor well above the
surrounding grade. Code wants 6" of fall in the first 10 feet
away from the building as a minimum. So do you. You've not said
what the garage was to be made of other than planning on a wood
sill plate. Brick/siding/wood frame It would be best to have
sheathing and/or siding to lap below the slab edge to seal the
weather away. You will need at least 6" of concrete exposed below
the siding for termites and rot, and then the six inches of fall.
Many guys plan to form and pour the footing and slab at the same
time. It is also fine to pour a footing and then form a stem wall
or slab on top of the footing. The forms need to extend at least
to the top of the slab, or extend a stem wall above the floor
level to help with grade issues. It can be difficult to edge form
at the outside of the footing as you cannot drive stakes, thus why
many guys pour monolithic.

4) I will then place my forms (2X8s) and make sure everything is
of correct size and square up the forms.

If the 2x8 is an edge form, it is marginal at best, though this is
subject to footing height. How are you planning to hold and brace
the 2x8's? I hope you have batter boards up for the footing
excavation already, they should be set to line and grade.

5) I will place my 6X6 10 Gauge wire mesh to the footer

Remesh should be set on blocks before the pour. It has little or
no value at the footing. It does nothing to strengthen the
concrete, it is there to reduce crack separation. I would prefer
not using it were it mine. Spend the time/money/effort on well
compacted subgrade. If you parking tractors or buses, increase
the depth of concrete and consider rebar reinforcement. You've
not ever indicated what depth of concrete you intend.

6) I will then have the concrete brought in and will pour and
level out with a Bull float/screeds/maybe even a power trowel.

It is just a semantics problem. You set screeds to be able to
"rod" the concrete. Once you have rodded the concrete to grade,
you use a bull float to flatten, bring cream to the top, and fill
and densify small holes. This is too much concrete for one man
with limited experience. Make sure the bleed water comes off
before you begin any type of finishing. Knee boards, hand float,
and 2 trips with a hard trowel or power float and power trowel.
If you have not ever used one, find someone who has.

7) I will then place the garage bolts for the sill board

Set all J bolts in templates nailed to the forms. Do your
go-zintas before the pour. They need to go into pretty wet
concrete, you might as well get em set beforehand.

8) Spray on curing agent

Are you casting recessed pockets for the overhead door(s). Level
floor rather than pitched to drain or door? Are you casting a
brick or sheathing pocket around the perimeter? If so, make sure
to omit at doors and openings.


--
______________________________
Keep the whole world singing . . . .
DanG (remove the sevens)
dgriff237@7cox.net



> All,
> I am working on adding two garages on my property. The larger is
> a
> 24X32 and the smaller one is 14X20. My father was in
> construction and
> I have done about everything in-home construction, except, major
> concrete. I have done sidewalks, patios, etc but nothing major.
> This
> is where my questions originate.
>
> I have read a few books and gotten my permits. I marked out the
> location of the new garages and squared them up over last week
> after
> work. Then last weekend, I broke ground with an excavator and a
> large
> bobcat. Knowing that I would be better off (concrete savings)
> having a
> professional dig the actual footer, I hired a friend of a friend
> to
> dig my footer and I operated the bobcat. Things went as expected
> and
> my figures for stone and supplies came out. I am preparing for
> inspection and this morning I cleared out the roots from a few
> trees
> that sit in the back 30 feet of my property. I am planning on
> pouring
> the footer then the finished slab.
>
> The one thing that I am concerned about is during the excavation
> we
> ran into two leach fields (at 3 feet down), an old septic leach
> bed
> and a leach bed from an old gray water system (at 2 feet down).
> I am
> positive that these systems are both no longer used and the main
> tanks
> are filled with sand. I know this for certain because I did this
> and
> the new sewer line to the house (120 feet)with my dad when the
> city
> sewer came to our area about 10 years ago. The septic system was
> original with the house (50 years old) and was about 200 gallons
> (very
> very small) and the leach field was only 120 feet in a Y. The
> gray
> water system ran the washing machine and dishwasher only and was
> 110
> gallons and had only a 45 feet leach system but had a very large
> diameter.
>
> How is something like this normally handled?
>
> I have, so far, crushed and removed them from the footer
> entirely and
> have filled them with foam and packed the ends with dirt and
> stone
> tightly. There was no water in either system as expected.
>
> Are these pipes even a concern at this point?
>
> My next question is concerning the next steps in the concrete
> process.
>
> My plans, and please correct me if I am wrong, is the following;
>
> 1) I will get approval from the city that my footer and stone
> etc is
> good.
> I assume they are mostly concerned with depth, width, and
> straightness
> of the footer and the stone is 4 inch or better.
> 2) I will rebar the footer
> 3) I will bring in the concrete and pour the footer to the
> bottom of
> the stone. (stone started 4 inches below earth grade)
> 4) I will then place my forms (2X8s) and make sure everything is
> of
> correct size and square up the forms.
> 5) I will place my 6X6 10 Gauge wire mesh to the footer
> 6) I will then have the concrete brought in and will pour and
> level
> out with a Bull float/screeds/maybe even a power trowel.
> 7) I will then place the garage bolts for the sill board
> 8) Spray on curing agent
>
> Now, I am considering having the above done after I get approval
> from
> the city inspection. As I have a friend who has a friend that
> does
> this for a living. I have seen his work and I think it looks
> decent.
> So everyone knows, this is very against my grain as I hire very
> few
> things out. My main concern is the man power behind this and the
> skill
> to do the final level/finish but I know getting to this point is
> a
> very big step.
>
> Now what should I expect to pay outside the cost of materials to
> have
> him do this? What is the norm? I have been told he will bring in
> 4
> guys at $250 a day for the actual pour. What should form, rebar
> and
> mesh placement cost me?
>
> I have another option to finish this concrete which is decent as
> well.
> I personally have a long time friend that is in the heavy
> machine
> operating trade (40 + years) and has done a lot of large scale
> concrete/masonry in his life. I have seen his work and it is
> decent.
>
> Any opinions or suggestions?
>
> Sorry for the rambling.
>
> Thanks,
> Chris
> Solomon_Man
>



Posted by Solomon_Man on May 31, 2007, 4:14 pm
> If the old lines crossed the footing, no big deal. If they ran
> the same way as the footing, you need to worry about compaction
> and dig down to undisturbed soil. An 8 inch pipe you can cut with
> a knife sounds huge for gray water, sounds more like an area
> drain. Deal with it after you stabilize the area.
>
> My plans, and please correct me if I am wrong, is the following;
>
> 1) I will get approval from the city that my footer and stone etc
> is good. I assume they are mostly concerned with depth, width,
> and straightness of the footer and the stone is 4 inch or better.
>
> What stone? Yes, they will be looking for frost depth. Footing
> inspection here would expect the steel in location, tied,
> supported, proper distance from dirt, correct laps, and corner
> bars. They really don't care if it is straight or over wide -
> those are things you need.
>
> 2) I will rebar the footer
>
> See above. Code here demands 2 #5 continuous, lapped 32 bar
> diameters where necessary, corner bars tied in.
>
> 3) I will bring in the concrete and pour the footer to the bottom
> of the stone. (stone started 4 inches below earth grade)
>
> The inspector may demand that reinforcing steel tie the slab to
> the footing, I would J bolts should extend into the reinforced
> footing zone. I guess you are talking about a gravel sub base
> under the slab. You will want finish floor well above the
> surrounding grade. Code wants 6" of fall in the first 10 feet
> away from the building as a minimum. So do you. You've not said
> what the garage was to be made of other than planning on a wood
> sill plate. Brick/siding/wood frame It would be best to have
> sheathing and/or siding to lap below the slab edge to seal the
> weather away. You will need at least 6" of concrete exposed below
> the siding for termites and rot, and then the six inches of fall.
> Many guys plan to form and pour the footing and slab at the same
> time. It is also fine to pour a footing and then form a stem wall
> or slab on top of the footing. The forms need to extend at least
> to the top of the slab, or extend a stem wall above the floor
> level to help with grade issues. It can be difficult to edge form
> at the outside of the footing as you cannot drive stakes, thus why
> many guys pour monolithic.
>
> 4) I will then place my forms (2X8s) and make sure everything is
> of correct size and square up the forms.
>
> If the 2x8 is an edge form, it is marginal at best, though this is
> subject to footing height. How are you planning to hold and brace
> the 2x8's? I hope you have batter boards up for the footing
> excavation already, they should be set to line and grade.
>
> 5) I will place my 6X6 10 Gauge wire mesh to the footer
>
> Remesh should be set on blocks before the pour. It has little or
> no value at the footing. It does nothing to strengthen the
> concrete, it is there to reduce crack separation. I would prefer
> not using it were it mine. Spend the time/money/effort on well
> compacted subgrade. If you parking tractors or buses, increase
> the depth of concrete and consider rebar reinforcement. You've
> not ever indicated what depth of concrete you intend.
>
> 6) I will then have the concrete brought in and will pour and
> level out with a Bull float/screeds/maybe even a power trowel.
>
> It is just a semantics problem. You set screeds to be able to
> "rod" the concrete. Once you have rodded the concrete to grade,
> you use a bull float to flatten, bring cream to the top, and fill
> and densify small holes. This is too much concrete for one man
> with limited experience. Make sure the bleed water comes off
> before you begin any type of finishing. Knee boards, hand float,
> and 2 trips with a hard trowel or power float and power trowel.
> If you have not ever used one, find someone who has.
>
> 7) I will then place the garage bolts for the sill board
>
> Set all J bolts in templates nailed to the forms. Do your
> go-zintas before the pour. They need to go into pretty wet
> concrete, you might as well get em set beforehand.
>
> 8) Spray on curing agent
>
> Are you casting recessed pockets for the overhead door(s). Level
> floor rather than pitched to drain or door? Are you casting a
> brick or sheathing pocket around the perimeter? If so, make sure
> to omit at doors and openings.
>
> --
> ______________________________
> Keep the whole world singing . . . .
> DanG (remove the sevens)
> dgriff...@7cox.net
>
>
>
>
>
> > All,
> > I am working on adding two garages on my property. The larger is
> > a
> > 24X32 and the smaller one is 14X20. My father was in
> > construction and
> > I have done about everything in-home construction, except, major
> > concrete. I have done sidewalks, patios, etc but nothing major.
> > This
> > is where my questions originate.
>
> > I have read a few books and gotten my permits. I marked out the
> > location of the new garages and squared them up over last week
> > after
> > work. Then last weekend, I broke ground with an excavator and a
> > large
> > bobcat. Knowing that I would be better off (concrete savings)
> > having a
> > professional dig the actual footer, I hired a friend of a friend
> > to
> > dig my footer and I operated the bobcat. Things went as expected
> > and
> > my figures for stone and supplies came out. I am preparing for
> > inspection and this morning I cleared out the roots from a few
> > trees
> > that sit in the back 30 feet of my property. I am planning on
> > pouring
> > the footer then the finished slab.
>
> > The one thing that I am concerned about is during the excavation
> > we
> > ran into two leach fields (at 3 feet down), an old septic leach
> > bed
> > and a leach bed from an old gray water system (at 2 feet down).
> > I am
> > positive that these systems are both no longer used and the main
> > tanks
> > are filled with sand. I know this for certain because I did this
> > and
> > the new sewer line to the house (120 feet)with my dad when the
> > city
> > sewer came to our area about 10 years ago. The septic system was
> > original with the house (50 years old) and was about 200 gallons
> > (very
> > very small) and the leach field was only 120 feet in a Y. The
> > gray
> > water system ran the washing machine and dishwasher only and was
> > 110
> > gallons and had only a 45 feet leach system but had a very large
> > diameter.
>
> > How is something like this normally handled?
>
> > I have, so far, crushed and removed them from the footer
> > entirely and
> > have filled them with foam and packed the ends with dirt and
> > stone
> > tightly. There was no water in either system as expected.
>
> > Are these pipes even a concern at this point?
>
> > My next question is concerning the next steps in the concrete
> > process.
>
> > My plans, and please correct me if I am wrong, is the following;
>
> > 1) I will get approval from the city that my footer and stone
> > etc is
> > good.
> > I assume they are mostly concerned with depth, width, and
> > straightness
> > of the footer and the stone is 4 inch or better.
> > 2) I will rebar the footer
> > 3) I will bring in the concrete and pour the footer to the
> > bottom of
> > the stone. (stone started 4 inches below earth grade)
> > 4) I will then place my forms (2X8s) and make sure everything is
> > of
> > correct size and square up the forms.
> > 5) I will place my 6X6 10 Gauge wire mesh to the footer
> > 6) I will then have the concrete brought in and will pour and
> > level
> > out with a Bull float/screeds/maybe even a power trowel.
> > 7) I will then place the garage bolts for the sill board
> > 8) Spray on curing agent
>
> > Now, I am considering having the above done after I get approval
> > from
> > the city inspection. As I have a friend who has a friend that
> > does
> > this for a living. I have seen his work and I think it looks
> > decent.
> > So everyone knows, this is very against my grain as I hire very
> > few
> > things out. My main concern is the man power behind this and the
> > skill
> > to do the final level/finish but I know getting to this point is
> > a
> > very big step.
>
> > Now what should I expect to pay outside the cost of materials to
> > have
> > him do this? What is the norm? I have been told he will bring in
> > 4
> > guys at $250 a day for the actual pour. What should form, rebar
> > and
> > mesh placement cost me?
>
> > I have another option to finish this concrete which is decent as
> > well.
> > I personally have a long time friend that is in the heavy
> > machine
> > operating trade (40 + years) and has done a lot of large scale
> > concrete/masonry in his life. I have seen his work and it is
> > decent.
>
> > Any opinions or suggestions?
>
> > Sorry for the rambling.
>
> > Thanks,
> > Chris
> > Solomon_Man- Hide quoted text -
>
> - Show quoted text -

All,
The inspector came out and inspected, I got approved.

He said the pipes are no big deal as the tanks are sanded. Rebar and
mesh are not required but I am still going to do it to avoid the
cement from pulling apart if I ever have a problem.

The question now in my head is to do it myself or have someone do it.
The inspector said to do it myself. He said you did a fine job
(depth,width,straightness,stone,layout) on the excavation and that is
where most people screw up. So I now understand the process even more
after talking to the inspector, so I am thinking more about doing it
myself to save the cash. I dunno, I will price it out and make the
final decision.

I plan to put electrical in and will install what is necessary for
that in the concrete before I pour. I will not actually do electrical
till next year as the whole property will be upgraded.

Thanks for the help.

Chris


Posted by Dave on June 1, 2007, 1:33 am
> All,
> I am working on adding two garages on my property. The larger is a
> 24X32 and the smaller one is 14X20. My father was in construction and
> I have done about everything in-home construction, except, major
> concrete. I have done sidewalks, patios, etc but nothing major. This
> is where my questions originate.
>
> I have read a few books and gotten my permits. I marked out the
> location of the new garages and squared them up over last week after
> work. Then last weekend, I broke ground with an excavator and a large
> bobcat. Knowing that I would be better off (concrete savings) having a
> professional dig the actual footer, I hired a friend of a friend to
> dig my footer and I operated the bobcat. Things went as expected and
> my figures for stone and supplies came out. I am preparing for
> inspection and this morning I cleared out the roots from a few trees
> that sit in the back 30 feet of my property. I am planning on pouring
> the footer then the finished slab.
>
> The one thing that I am concerned about is during the excavation we
> ran into two leach fields (at 3 feet down), an old septic leach bed
> and a leach bed from an old gray water system (at 2 feet down). I am
> positive that these systems are both no longer used and the main tanks
> are filled with sand. I know this for certain because I did this and
> the new sewer line to the house (120 feet)with my dad when the city
> sewer came to our area about 10 years ago. The septic system was
> original with the house (50 years old) and was about 200 gallons (very
> very small) and the leach field was only 120 feet in a Y. The gray
> water system ran the washing machine and dishwasher only and was 110
> gallons and had only a 45 feet leach system but had a very large
> diameter.
>
> How is something like this normally handled?
>
> I have, so far, crushed and removed them from the footer entirely and
> have filled them with foam and packed the ends with dirt and stone
> tightly. There was no water in either system as expected.
>
> Are these pipes even a concern at this point?
>
> My next question is concerning the next steps in the concrete process.
>
> My plans, and please correct me if I am wrong, is the following;
>
> 1) I will get approval from the city that my footer and stone etc is
> good.
> I assume they are mostly concerned with depth, width, and straightness
> of the footer and the stone is 4 inch or better.
> 2) I will rebar the footer
> 3) I will bring in the concrete and pour the footer to the bottom of
> the stone. (stone started 4 inches below earth grade)
> 4) I will then place my forms (2X8s) and make sure everything is of
> correct size and square up the forms.
> 5) I will place my 6X6 10 Gauge wire mesh to the footer
> 6) I will then have the concrete brought in and will pour and level
> out with a Bull float/screeds/maybe even a power trowel.
> 7) I will then place the garage bolts for the sill board
> 8) Spray on curing agent
>
> Now, I am considering having the above done after I get approval from
> the city inspection. As I have a friend who has a friend that does
> this for a living. I have seen his work and I think it looks decent.
> So everyone knows, this is very against my grain as I hire very few
> things out. My main concern is the man power behind this and the skill
> to do the final level/finish but I know getting to this point is a
> very big step.
>
> Now what should I expect to pay outside the cost of materials to have
> him do this? What is the norm? I have been told he will bring in 4
> guys at $250 a day for the actual pour. What should form, rebar and
> mesh placement cost me?
>
> I have another option to finish this concrete which is decent as well.
> I personally have a long time friend that is in the heavy machine
> operating trade (40 + years) and has done a lot of large scale
> concrete/masonry in his life. I have seen his work and it is decent.
>
> Any opinions or suggestions?
>
> Sorry for the rambling.
>
> Thanks,
> Chris
> Solomon_Man
>

What I don't understand is you stated you knew all this was there, did the
prep work, and intial excavations, now you're inquiring about its use as
base under a foundation for garages.

My consideration, if knowing all this in advance, not advisable.
Dave



Similar ThreadsPosted
Quick Questions concerning Rough Construction and building a garage...... September 11, 2007, 10:08 am
Dumb questions re: 2 x 6 construction August 18, 2006, 3:27 am
Post Frame Construction questions (Cost) July 17, 2007, 1:56 am
What to Know Before Starting Garage Construction September 8, 2007, 7:36 am
Concrete garage base August 11, 2006, 9:09 am
How to remove concrete from vinyl garage door? July 2, 2006, 10:57 am
Construction of Concrete Water Storage Tank January 7, 2007, 7:24 am
Questions for Contractor's January 9, 2007, 9:09 am
Screened Porch questions July 19, 2006, 4:44 pm
Steel building questions August 12, 2006, 1:25 am

Contact Us | Privacy Policy

XML SitemapXML Sitemap