|
Posted by on August 18, 2007, 8:43 pm
> Rebar exposed to dirt should have 3 inches of cover. Formed
> concrete should have 1 1/2" of cover. Most curbs do not have
> steel. They do have load transfer dowels at joints - these are 1"
> thick slick dowels about a foot long.
>
> In commercial work, the 4 bars in the footing would typically have
> #3 cages (stirrups) at a particular spacing, usually 12" c-c.
> These beam reinforcements are usually hung in the forms, spaced
> away from form surfaces, and poured.
>
> The Corps of Engineers and other architectural concrete agencies
> will not allow driving pins in the dirt to support reinforcement.
> The contention is that said rebar will rust and the rust will get
> into the rest of the reinforcement.
>
> There are sure many installations on driven pins. I have dug up
> old work that has been in the ground for over 50 years where the
> rust had no gotten to the pins in the dirt, much less the grade
> beam steel. I have dug up old footings, etc where the cage steel
> was exposed to the dirt (was not spaced away and covered
> properly), the rebar had rust, but was very viable.
>
> Your call. It's your stuff. If the fellas are making an honest
> effort at holding the steel to grade, providing temporary spacers
> to keep the steel away from the dirt, plan to use a vibrator, and
> can show other pours with a decent finish, I think I would leave
> them alone. These issues should have all been resolved before
> they ever started, to change now sounds like a recipe for
> disaster.
>
> --
> ______________________________
> Keep the whole world singing . . . .
> DanG (remove the sevens)
> dgriff...@7cox.net
>
>
>
>
>
> >I am having a monolithic slab poured (25' x 30') with 16" (w) x
> > 18" (d) footings. 18" is below the frost line in my area. This
> > slab
> > will also have a 6" (h) x 4 1/2" (w) curb along the outside
> > edge. I
> > am a little concerned about the quality of the work by the
> > contractor. My questions: Should the curb have re-bar? If so,
> > what
> > size? There will be anchor bolts (j bolts) 4' o.c. along the
> > curb.
> > How should the re-bar (#4 (1/2')) be set in the footings? By
> > that I
> > mean how far below the surface should the top re-bar be? There
> > are 4
> > lines of rebar in the footing, two near the bottom and two near
> > the
> > top. In my layman opinion, the top set is too close to the
> > surface.
> > Also, the re-bar is tied to a vertical length of rebar driven
> > into the
> > ground. Is this acceptable? Any comment will be appreciated.- Hide quoted
text -
>
> - Show quoted text -
Thank you very much DanG for that response. I know very little about
concrete work and thus don't know quality when I see it. Plumbing,
electrical and roofing I know well enough to make sure I'm getting a
quality job.
|