|
Posted by Bob Morrison on November 15, 2006, 7:11 pm
In a previous post Chuck wrote...
> Researching a bit I've found some details described here concerning shear
> keys and oiled dowels in addition to how to make various connections
> between pours. Do you think an oiled dowel joint would be sufficient?
> http://www.usace.army.mil/publications//////////armytm/tm5-822-5/chap15.pdf
For light traffic an oiled dowel w/o shear key is probably okay.
>
> > For hand mixed concrete you will probably not be able to pour more than
> > 9'x 14' in a day. So, it won't be necessary to cut crack control
> > joints, but you will need some method for transferring shear between one
> > day's pour and the next.
> >
> From work we've done in the past, your estimate(9'x14'x5"= 52.5cft) seems
> reasonable but I've got to figure out a way to do much more.
> Otherwise(according to my calculations) it will take 38 days to pour the
> slabs alone. The plan is to start at the top and work our way down
> because materials can be dropped at the top and it's easier to move them
> downhill than up. Also it's going to help if at least some people can use
> the top portion of the road before the lower section is able to be driven
> upon.
>
> > For compaction of subgrade, use a loaded dump truck or other heavy
> > vehicle. For compaction of gravel base see if you can rent a Jumping
> > Jack. If not then you can run the heavy truck over the gravel and use
> > hand compaction methods for as needed.
> >
> If a heavy truck were to be used for compaction, how deep of a gravel bed
> do I want(and what size gravel should be used?) As for actually
> compacting the gravel, I'm curious how that works. Are the rocks really
> getting pressed together tighter or are they being pressed into the
> topsoil?? Sorry for asking such basic questions but from what I
> gather this stage is crucial to the longevity of the drive and I'm
> pretty fuzzy on it's function in general. I also worry about water
> undermining the entire road if it seeps below the slab in places such as
> the uncovered center section. Is this a legitimate concern?
You want to end up with 6" of compacted thickness. I usually recommend
3/4" minus crushed rock. If you are concerned about pushing the gravel
into soft soil then use a geotextile between the gravel and soil.
Otherwise, compact the soil first then apply and compact the gravel layer.
The gravel layer is intended to be free-draining. Water should pass
through it. You could excavate a deeper section in the middle of the an
install a "french" drain, but given the slope of the driveway I don't
think water will be of much concern as long as you have drainage ditches.
--
Bob Morrison, PE, SE
R L Morrison Engineering Co
Structural & Civil Engineering
Poulsbo WA
bob at rlmorrisonengr dot com
|