Posted by Alan on August 12, 2006, 3:16 am
Ok, my 10,000lb reactions per point load on the garage dormer trusses
are known to require a 3-1/2 cubed footing of concrete to support the
load. So, I have the tough job of cutting into the garage floor,
digging a big hole around and under the existing perimeter foundation
footer of the garage, and pouring a lot of concrete and rebar. It's
been suggested that I go ahead and consider cutting through the
existing footer to make the job easier.
But, now I'm interested whether or not the two 8' long 4x12 garage door
headers (plus double top plate across both) can support the point load
of the trusses. I can't figure out how to convert reactions numbers
into load or forces down on the header. Span tables aren't of any
apparent help. Obviously, I want minimum deflection and no structural
breakage for these headers.
I have been told by my truss designer that my 2x4 stud wall will hold
the point loads, so it seems possible, but I'm still concerned about
whether the headers can. To clarify, I have two 8' wide garage doors
with 4x12 headers, and a central 8" wide post of several 2x4s (I may
swap this out for a 3" steel post, swapping headers is more difficult).
In any case, each door header takes the load of one of the heavy truss
point loads, and the point loads of lighter trusses, all spaced 24"OC.
I'm trying to solve this while my engineer finds time to fit me into
his schedule. Previous help was interesting, so I'd like to understand
more about how the trusses will affect my existing headers.
Posted by Italian on August 12, 2006, 11:20 am
show/hide quoted text
I cant speak to the other issues other than it sounds like regardless
of what you use the footing needs to be increased. If you have access
to the entire perimiter of the garage from the outside you do not need
to do this from the inside. You can sister on the additional footing
next to the existing footing from the outside. In general this involves
drilling in to the existing footing at specified intervals epoxying
rebar to tie the 2 together plus a bunch more crap. Since you have an
engineer he can make up a detail based on the existing footing and what
modification you need to make to it work.....that is if you can get him
to take your calls.....been there...
show/hide quoted text
Yea and your paying him..dont you love it...
Alan wrote:
show/hide quoted text
Similar ThreadsPosted
Truss Calculations Point Load Errors! Help August 4, 2006, 10:00 pm
HVAC calculations May 11, 2008, 5:39 pm
Is my sunroom included in square footage calculations? December 2, 2006, 8:42 pm
Vanity top installation issue September 4, 2007, 8:06 pm
retaining wall issue March 19, 2008, 4:26 pm
Quality issue with LVL header in basement? December 28, 2006, 10:45 pm
Wood-I or Open Truss Joists? April 25, 2008, 8:35 am
Re: Wood-I or Open Truss Joists? May 1, 2008, 11:32 am
Concrete guy with issue has an Asphalt question from you experts April 19, 2008, 10:02 am
Blocking in Basement between open Truss and rim joist November 20, 2006, 3:33 pm

Contact Us | Privacy Policy

XML SitemapXML Sitemap