UK Building Regs query Jim 10-18-2007
If you were  Registered and logged in, you could reply and use other advanced thread options
Posted by Jim on October 18, 2007, 7:11 am
Can anyone help please? I have just submitted full building regs for a new
dwelling but the L.A. are taking 8 weeks to approve and I wish to start
a.s.a.p. Someone has suggested that once they have been registered I can
begin provided I give the L.A. 48 hours notice of work.

Can anyone confirm this is correct and the rules that apply. Many thanks.

Regards
Jimbo



Posted by PeterD on October 18, 2007, 8:42 am
wrote:

>Can anyone help please? I have just submitted full building regs for a new
>dwelling but the L.A. are taking 8 weeks to approve and I wish to start
>a.s.a.p. Someone has suggested that once they have been registered I can
>begin provided I give the L.A. 48 hours notice of work.
>
>Can anyone confirm this is correct and the rules that apply. Many thanks.
>
>Regards
>Jimbo
>

I'm not sure what the 'L.A.' is, but did you ask them? Asking a bunch
of strangers on the Internet won't give you an answer you can trust,
but asking the *right* people will. Ask the 'L.A.' and see what they
say.

Posted by CWatters on October 18, 2007, 4:05 pm

> Can anyone help please? I have just submitted full building regs for a new
> dwelling but the L.A. are taking 8 weeks to approve and I wish to start
> a.s.a.p. Someone has suggested that once they have been registered I can
> begin provided I give the L.A. 48 hours notice of work.
>
> Can anyone confirm this is correct and the rules that apply. Many thanks.
>

Normally they will let you proceed upto to the point where the first
inspection is due. That's typically when you have dug (but not filled) the
foundation trenches. If in doubt give the Building Control Officer a call to
ask if that's ok. Once you are up and running they will usually come out
"next day" or even "same day" if you call first thing before they have
planned their day. Obviously they prefer a bit of notice.

Just bear in mind that it's not a good idea to have the trenches open too
long. Try and get them dug and filled as soon as possible to minimise the
risk of them filling with rain water, collapsing etc

I also recommend you join the forums at:

http://www.ebuild.co.uk/cgi-bin/forums/discus.pl
and
www.askthetrades.co.uk

The ebuild forum is the best for selfbuild. It's a bit difficult to use as
there are so many categories and sub categories but lots of good advice
there. Most of us resort to clicking on the links that says "Last 1|3|7
Days"

See you there!

Colin



Similar ThreadsPosted
Clear Span Query January 3, 2007, 12:25 am
Structural framing query February 18, 2007, 12:25 am
Cob Building December 29, 2006, 4:31 pm
building materials September 17, 2006, 11:24 am
Storage Building October 10, 2006, 2:03 pm
Old Wooden Building-help November 16, 2006, 6:39 am
Building a new school January 23, 2007, 7:04 am
pole building February 25, 2007, 1:40 pm
alt.building.electrical? April 2, 2007, 8:44 pm
Building Codes November 13, 2007, 3:07 am

Contact Us | Privacy Policy

XML SitemapXML Sitemap