Posted by jloomis on June 25, 2008, 9:50 am
I always put a layers of sand between the old concrete and the new.
I also use a vapor barrier.....below the sand......This allows for upper
slab movement......
In some ways like shipping glass in a package........
Do you put the 2 together and ship or do you separate them with bubble wrap
and send?
jloomis
>
>
> -------------------------------------
>
> I am pouring a 4" concrete slab (91'x60') over an existing slab inside a
> machine shop. Should I use a bond breaker or a bonding agent for this
> application. Also, should I use a pea gravel aggregate or standard 4000#
> mix?
>
>
> ##-----------------------------------------------##