Home Page link

electrical detached garage ? - Page 12

Building Construction - Building Construction Industry Discussions. 

Page 12 of 13       < 1 2 3 > last >> Bookmark this page:  YahooMyWeb Yahoo!  Google Google  Windows Live Favorites Windows Live  del.icio.us del.icio.us  digg digg  Add to Netscape Netscape
Subject Author Date
electrical detached garage ? jamesgangnc 02-23-2009
If you were  Registered and logged in, you could reply and use other advanced thread options
Posted by John Grabowski on March 2, 2009, 9:27 pm
show/hide quoted text
I had an extra ground rod concern (had one, needed an additional one)
a while back. The inspector suggested use of a single ground plate
(approx. 15" x 20") instead of the ground rod array. The plate was
only 30" deep. This was in northern Ontario. I didn't see plates
mentioned up-thread.
*The plate is certainly a viable and approved option.
Posted by Dioclese on March 3, 2009, 9:52 am
show/hide quoted text
The garage slab and driveway were constructed, poured, and finished by a
company that normally does commercial slabs and county road needs. The
garage has the standard rebar beam perimeter, remainder has bags with fill
overlaid with rebar. I don't know the gauge of the rebar. The rebar was
thicker in the beams than the remainder. The rebar in the remainder was
thicker than that used in the driveway. They also went out of their way to
put a miniature beams (not rebar reinforced vertically) on the driveway
perimeter.
I went by the NEC available and approved at the time in the late 2004 era.
As did the house builder. Both the house and detached garage have their own
single grounding 8' bar (copper), #4 copper bare wire and copper crimp
clamp.
show/hide quoted text
Which explains why the inspector don't do such tests... They just enforce
code, not establish if something meets code with testing. The 2 grounding
bar is his out.
--
Dave
CDOs are how we got here.
A modified version, new taxes in the future, is how Congress will get us
out?
Posted by Wayne Whitney on March 3, 2009, 12:10 pm
show/hide quoted text
Since as far as I know #3 bar is the smallest normally used in
construction, if the rebar in the beams is thicker than #3, it is
thick enough to be as part of a concrete encased electrode.
show/hide quoted text
To answer your other question, here at least the code version in
effect at the time of permitting applies to the project; I'm not aware
of any jurisdictions that would apply a newly adopted code to ongoing
projects, but perhaps there are some.
Under the 2002 NEC, the requirement on which electrodes to use said to
use all "available" electrodes. This led to a debate about the
concrete encased electrodes. On the one hand, for new construction,
they are available in the sense that with proper planning you could
use them. On the other hand, common construction practice was for
building sites never to see an electrician until well after the
foundation was poured, at which point the electrode was not
"available". Certainly I expect that under 2002 NEC, there were not
many inspectors requiring the use of the concrete encased electrodes.
The 2005 NEC clarified this by changing "available" to "present".
Nowadays there are plenty of jurisdictions where the builder will be
required to jack out concrete to access the rebar if they fail to
connect to it as a conrete-encased electrode.
Hope this helps.
Cheers, Wayne
Posted by jamesgangnc on March 4, 2009, 7:40 am
show/hide quoted text
That's just stupid. If they are not accessible then they are not
present. I'll drive a couple copper clad rods.
Posted by Wayne Whitney on March 4, 2009, 12:00 pm
show/hide quoted text
This only applies to new construction. The rebar is certainly
accessible before the concrete is poured, and it is the builder's
responsibility to see to it that it is use as a grounding electrode.
Cheers, Wayne
Page 12 of 13       < 1 2 3 > last >>
Similar ThreadsPosted
Adding 2nd floor above detached garage March 18, 2007, 7:07 pm
How do I install a drain in my detached garage? February 4, 2009, 2:32 pm
adequate spacing between detached garage and house? August 19, 2006, 12:37 pm
detached garage insulation- vapor barrier needed? August 10, 2006, 10:27 am
Adding Electrical To garage September 29, 2008, 8:33 am
Electrical Wiring Q July 20, 2006, 8:50 pm
ELECTRICAL QUESTION November 29, 2006, 10:24 pm
alt.building.electrical? April 2, 2007, 8:44 pm
Electrical Professional May 4, 2008, 4:26 pm
Electrical: centralized breakerbox November 19, 2006, 8:52 pm

Contact Us | Privacy Policy

XML SitemapXML Sitemap