Anchoring an outbuilding -sequence of events?

Home Repair - - If it ain't broken, don't fix it. Otherwise look here. 

Bookmark this page:  YahooMyWeb Yahoo!  Google Google  Windows Live Favorites Windows Live  del.icio.us del.icio.us  digg digg  Add to Netscape Netscape
Subject Author Date
Anchoring an outbuilding -sequence of events? Bill Stock 04-19-2007
If you were  Registered and logged in, you could reply and use other advanced thread options
Posted by Bill Stock on April 19, 2007, 8:15 pm


I mentioned yesterday that I want to build a pump house for the pond. My
original thought was to build the frame (4x4s) first and then cement the
legs in the post holes. But after doing a little reading, I'm not sure this
is a bright idea. Because it might be hard to get the footings level in all
four post holes. It would seem better to cut the posts to length AFTER they
are hardened up. I could still join the posts together with the crossers
while the cement is soft to get the horizontal spacing I want.

(The above seems kinda obvious now, but any countervailing opinions welcome)

I know I could use saddles, but I've not read good things about PT wood and
metal. I'm also concerned about the leverage the water wheel may exert on
the wood in the saddles. The pump house will also have about a 1,000 pounds
of water inside.





Similar ThreadsPosted
outbuilding electrical disconnect August 27, 2006, 1:18 pm
OT: A Pic Log of Katrina Events September 11, 2005, 9:55 am
Re: Construction sequence March 20, 2007, 7:00 pm
Re: Construction sequence March 23, 2007, 6:06 am
ASKO SECRET button sequence April 24, 2008, 11:19 pm
Washing Machine Timer Dial Out of Sequence November 12, 2005, 6:04 pm
Install sequence - Interior doors & laminate floor June 29, 2008, 9:53 pm
anchoring building down June 21, 2006, 4:40 am
Anchoring new shed to existing pad? May 18, 2007, 12:41 pm
Anchoring a Canopy onto Patio June 13, 2008, 9:20 pm

Contact Us | Privacy Policy

XML SitemapXML Sitemap