Posted by EXT on May 30, 2007, 5:23 pm
Check your building department, I think (I don't know) that they would only
require removal of the weeping tiles and possibly the contaminated gravel
from under your footers/foundation and not from under the floor.
Remember to add any conduit to feed wires, communications and possibly water
through the foundation floor and up into where the wall will be built. This
is especially important for the power line entering the building from
underground. You don't want this on the outside of the building when it is
so simple to enclose it in the foundation.
>>
>>
>>
>>
>>
>> > All,
>> > I am working on adding two garages on my property. The larger is a
>> > 24X32 and the smaller one is 14X20. My father was in construction and
>> > I have done about everything in-home construction, except, major
>> > concrete. I have done sidewalks, patios, etc but nothing major. This
>> > is where my questions originate.
>>
>> > I have read a few books and gotten my permits. I marked out the
>> > location of the new garages and squared them up over last week after
>> > work. Then last weekend, I broke ground with an excavator and a large
>> > bobcat. Knowing that I would be better off (concrete savings) having a
>> > professional dig the actual footer, I hired a friend of a friend to
>> > dig my footer and I operated the bobcat. Things went as expected and
>> > my figures for stone and supplies came out. I am preparing for
>> > inspection and this morning I cleared out the roots from a few trees
>> > that sit in the back 30 feet of my property. I am planning on pouring
>> > the footer then the finished slab.
>>
>> > The one thing that I am concerned about is during the excavation we
>> > ran into two leach fields (at 3 feet down), an old septic leach bed
>> > and a leach bed from an old gray water system (at 2 feet down). I am
>> > positive that these systems are both no longer used and the main tanks
>> > are filled with sand. I know this for certain because I did this and
>> > the new sewer line to the house (120 feet)with my dad when the city
>> > sewer came to our area about 10 years ago. The septic system was
>> > original with the house (50 years old) and was about 200 gallons (very
>> > very small) and the leach field was only 120 feet in a Y. The gray
>> > water system ran the washing machine and dishwasher only and was 110
>> > gallons and had only a 45 feet leach system but had a very large
>> > diameter.
>>
>> > How is something like this normally handled?
>>
>> > I have, so far, crushed and removed them from the footer entirely and
>> > have filled them with foam and packed the ends with dirt and stone
>> > tightly. There was no water in either system as expected.
>>
>> > Are these pipes even a concern at this point?
>>
>> > My next question is concerning the next steps in the concrete process.
>>
>> > My plans, and please correct me if I am wrong, is the following;
>>
>> > 1) I will get approval from the city that my footer and stone etc is
>> > good.
>> > I assume they are mostly concerned with depth, width, and straightness
>> > of the footer and the stone is 4 inch or better.
>> > 2) I will rebar the footer
>> > 3) I will bring in the concrete and pour the footer to the bottom of
>> > the stone. (stone started 4 inches below earth grade)
>> > 4) I will then place my forms (2X8s) and make sure everything is of
>> > correct size and square up the forms.
>> > 5) I will place my 6X6 10 Gauge wire mesh to the footer
>> > 6) I will then have the concrete brought in and will pour and level
>> > out with a Bull float/screeds/maybe even a power trowel.
>> > 7) I will then place the garage bolts for the sill board
>> > 8) Spray on curing agent
>>
>> > Now, I am considering having the above done after I get approval from
>> > the city inspection. As I have a friend who has a friend that does
>> > this for a living. I have seen his work and I think it looks decent.
>> > So everyone knows, this is very against my grain as I hire very few
>> > things out. My main concern is the man power behind this and the skill
>> > to do the final level/finish but I know getting to this point is a
>> > very big step.
>>
>> > Now what should I expect to pay outside the cost of materials to have
>> > him do this? What is the norm? I have been told he will bring in 4
>> > guys at $250 a day for the actual pour. What should form, rebar and
>> > mesh placement cost me?
>>
>> > I have another option to finish this concrete which is decent as well.
>> > I personally have a long time friend that is in the heavy machine
>> > operating trade (40 + years) and has done a lot of large scale
>> > concrete/masonry in his life. I have seen his work and it is decent.
>>
>> > Any opinions or suggestions?
>>
>> > Sorry for the rambling.
>>
>> > Thanks,
>> > Chris
>> > Solomon_Man
>>
>> If its a wood garage on a concrete slab I would make it a raised curb
>> perimeter to elminate all wood rot issues
>>
>> On the drain fileld I would dig it ALL out under the buildings and
>> backfill with ALL gravel- Hide quoted text -
>>
>> - Show quoted text -
>
> All,
> The tile for the leach field for the septic system is a orange ceramic
> - 3 or 4inch (very small) and the gray water system is a 8 inch pipe
> that is coming up to the front right corner of the garage. I was able
> to use a knife and cut the 8 inch pipe, with a pocket knife, one foot
> back completely away from the garage and its footer. The pipe is a
> thin black pipe very flexible with what seems to be clothe surrounding
> it. The 8 inch pipe was also at the end of its run and lucky for me
> ran till its end in my footer which of course I completely removed.
> The 8 inch pipe is not under the garage nor is it, at least in my
> opinion, a in the way problem. If the 8 inch is a problem I would
> prefer to remove it after the footer is poured as it goes back I am
> guessing 20 or so feet to the tank to avoid screwing up my footer
> walls and using excess concrete. The ceramic pipe is 3 feet down and
> my area soil is thick dark clay. The ceramic is somewhat of a concern
> but to remove it would require a complete diagonal cut across my 24X32
> garage at three foot. Before I would consider digging it up, I would
> look at options of filling it with solid concrete as it would only be
> a additional 1/2 yard (max) according to my figures.
>
> Just some more information.
>
> Thanks,
> Chris
> Solomon_Man
>
>
>
>
>
|