|
Posted by on July 8, 2006, 4:14 am
hilary@fashionsintime.com wrote:
> Norminn wrote:
> > wipeout64@hotmail.com wrote:
> > > It turns out the contractor we hired to paint our house is unreliable.
> > > He managed to get the primer on and some of the trim. The problem is
> > > that the can states that the top coat must be put on within 30 days. Is
> > > it absolutely necessary to stick to 30 days time limit? What would
> > > happen if it is 1 or 2 weeks over?
> > >
> > Have you had contact with him, tried, been given a reason for delay? My
> > unscientific opinion is that a couple of weeks won't hurt. Much longer,
> > and it might get dirty or oxidized a bit. Got a written bid with a time
> > stated for completion? Satisfied with his work otherwise? A lot would
> > depend on issues you have not stated. I don't trust AHR for legal
> > advice, but the paint label is "on your side" - job needs to be
> > completed. Unless he dropped dead, he should have contacted you to
> > explain the delay - good reason for hiring someone else.
>
> I'd be tempted to send him a certified letter stating that if the job
> is not completed by x date (30 days?) another painter will be hired.
> Inform him that he will only be paid the difference between the
> original contract and whatever the new painter charges you. Why should
> you have to pay twice for the same job? If you have a new painter give
> you an estimate to complete the job there's no way the first painter
> could recover his entire fee, since he didn't complete the job. At
> least that's the way it worked in small claims court in NY the one day
> I observed. I watched case after case where the judge asked if the
> homeowner had a completion estimate from new contractor, and then the
> judge gave the original contractor the difference between the new
> completion estimate and the original contract. In two cases, the
> original contractor had to pay the homeowner!
>
> As always, however, YMMV.
>
> Hilary
That sounds like good advice to me. A week or two beyond the 30 days
specified on the primer can probably isn't going to make any
difference. Also, that 30 days is specd as worse case, with high
temps, etc. In a more typical case, I doubt going 2 weeks beyond will
make a difference.
But, if the OP is dissatisfied with the performance of the contractor,
they should send a letter telling the contractor they want the job
finished in say 30 days. Also cite the concern about the primer. I
would stay away from who owes who what in the letter at this point. As
Hilary pointed out, if you have to get another contractor to finish the
job, and it cost more, the existing contractor can be sued for the
difference. Of oourse collecting a judgement is another matter.
Also, how long and how much you have to put up with is arguable. If
the contractor is making slow but steady progress, I'd be less
concerned than if he's disappered for a long time with no communication.
|