Figuring out what partial work is worth.

Home Repair - - If it ain't broken, don't fix it. Otherwise look here. 

Page 2 of 2       << first < 1 2 Bookmark this page:  YahooMyWeb Yahoo!  Google Google  Windows Live Favorites Windows Live  del.icio.us del.icio.us  digg digg  Add to Netscape Netscape
Subject Author Date
Figuring out what partial work is worth. edavid3001 12-13-2006
If you were  Registered and logged in, you could reply and use other advanced thread options
Posted by on December 14, 2006, 2:08 pm



Goedjn wrote:
> On 13 Dec 2006 20:31:43 -0800, edavid3001@gmail.com wrote:
>
> >First contractor -- paid ~$1400 for wood to frame basement. As soon as
> >wood arrived, he passed this job onto another contractor.
> >
> >We are 6 months into it and the second contractor has done most all of
> >the framing with some minor areas needing boxed & the inspectors minor
> >changes.
> >
> >He's also ran electrical, though I did have to pay another electrician
> >$1000 to finish up pre-framing electric work. I paid to have the
> >cable/phone/network ran myself.
> >
> >So this guy's done the framing for 1000 square feet, he has done
> >electric work, and he has purchased the drywall, tape, and mud. I
> >have since paid for a plumber..
> >
> >Anyway, this second guy walked off the job with $6000 paid to him. For
> >doing framing, some of the electrical, and purchasing the drywall
> >materials. He passed the job onto another person.
> >
> >I need to figure out how much what he did was worth, and I am not sure
> >how to do that. The drywall, while impressive looking down there, is
> >not that expensive afaik. We're talking maybe $500 for that material,
> >right? How can I try and calculate what the labor for the framing is
> >worth? It took him 6 months, but he would be gone for 3 weeks at a
> >time doing nothing to my basement. And then what the amount of
> >electrical work he did was worth? There is not an accounting of the
> >hours he worked so I can't simply do hours X $50 for example.
> >
> >This is a lower wage area, in a small US city.
> >
> >Thanks!
>
> If you have a contract, get someone else to finish, and
> pay the guy what walked whatever the difference is.
> If he wants more than that, make HIM justify it.



What does the guy say he wants? You've already paid $8500 to frame,
drywall and run electric to a 1000 sq ft basement area. That sounds
like plenty to me. The time to have established costs was upfront with
a written contract. Do you have anything in writing? Or what was the
verbal agreement you had?


PexSupply PEX Tools 468x60
Posted by on December 14, 2006, 6:41 pm



> > If you have a contract, get someone else to finish, and
> > pay the guy what walked whatever the difference is.
> > If he wants more than that, make HIM justify it.

Yes, I do have a contract. That sounds like a good idea to me.
Thanks.


> What does the guy say he wants? You've already paid $8500 to frame,
> drywall and run electric to a 1000 sq ft basement area. That sounds
> like plenty to me. The time to have established costs was upfront with
> a written contract. Do you have anything in writing? Or what was the
> verbal agreement you had?


We have a written contract. $13,000 to finish everything up with the
exception of the cost of the ceramic flooring materials. It did
include labor, though.

>> My guess is you are not entirely without fault. You probably made a
>>few design changes along the way, right? Those usually are billed at
>>top dollar.

The changes were no including three closets in three rooms which we
originally
planned on having. This was because the inspector told us prior to
work beginning
and after the contract that we could not have closets.

So that would be billed at top dollar, eh? Since that is work that was
planned
into the contract and not actually done, does that mean I get to deduct
top dollar
from the contract? Is that what you are saying?

Nothing has been added to the project. There was an elaborate draft of
the work to
be done made at the beginning. Details including how many electrical
outlets, their
location, number of light switches & their location, etc. We put this
together with the help of the contractor to prepare the bid.

If I am at fault for anything it is letting months pass with no work
getting done.


Posted by DK on December 14, 2006, 10:56 pm


On 14 Dec 2006 15:41:21 -0800, edavid3001@gmail.com wrote:

>
>> > If you have a contract, get someone else to finish, and
>> > pay the guy what walked whatever the difference is.
>> > If he wants more than that, make HIM justify it.
>
>Yes, I do have a contract. That sounds like a good idea to me.
>Thanks.
>
>
>> What does the guy say he wants? You've already paid $8500 to frame,
>> drywall and run electric to a 1000 sq ft basement area. That sounds
>> like plenty to me. The time to have established costs was upfront with
>> a written contract. Do you have anything in writing? Or what was the
>> verbal agreement you had?
>
>
>We have a written contract. $13,000 to finish everything up with the
>exception of the cost of the ceramic flooring materials. It did
>include labor, though.
>
>>> My guess is you are not entirely without fault. You probably made a
>>>few design changes along the way, right? Those usually are billed at
>>>top dollar.
>
>The changes were no including three closets in three rooms which we
>originally
>planned on having. This was because the inspector told us prior to
>work beginning
>and after the contract that we could not have closets.
>
>So that would be billed at top dollar, eh? Since that is work that was
>planned
>into the contract and not actually done, does that mean I get to deduct
>top dollar
>from the contract? Is that what you are saying?
>
>Nothing has been added to the project. There was an elaborate draft of
>the work to
>be done made at the beginning. Details including how many electrical
>outlets, their
>location, number of light switches & their location, etc. We put this
>together with the help of the contractor to prepare the bid.
>
>If I am at fault for anything it is letting months pass with no work
>getting done.

Well, then. Sometimes you just gotta do what you gotta do. So step
up to the plate and sue the bastards.




Posted by on December 18, 2006, 9:37 am


> >If I am at fault for anything it is letting months pass with no work
> >getting done.
>
> Well, then. Sometimes you just gotta do what you gotta do. So step
> up to the plate and sue the bastards.

That seems a little extreme to me. I took Goedjn's advice, and the
contractor thought it was fair. So we are square now. Thank you.


Page 2 of 2       << first < 1 2
Similar ThreadsPosted
Figuring Out Sprinkler GPM November 2, 2006, 4:14 pm
Figuring out my junction box March 20, 2007, 11:37 am
Partial tub re-caulking January 8, 2007, 4:12 am
Partial power outage? July 12, 2005, 8:57 pm
Partial insulation of pipes December 1, 2005, 3:54 pm
Partial power failure December 1, 2008, 5:27 pm
Toilet - partial flush problem September 29, 2006, 3:33 pm
Partial follow-up on 4" angle grinder January 14, 2007, 10:17 am