Posted by Steve Barker LT on December 12, 2006, 5:46 pm
Why not ask the folks doing the job?
--
Steve Barker
> Late yesterday afternoon I faxed my signed bid to the company who first
> bid on the job. Good references, by far the best price. Plus they
> actually ran a camera through the existing line and didn't charge me a
> cent. The other guys made their bids on the basis of inspection from
> above, only.
>
> Yesterday afternoon, when I faxed the bid, it was dry, but it rained
> something fierce overnight. There had been relatively little rain here
> until last night. Now the ground is going to be saturated. They have to
> dig at least 4 holes to get down to the existing clay lateral for
> connections and access to do the trenchless.
>
> What affect does the rain have on all this? Thanks for your answers.
|