Posted by Aaron Fude on December 5, 2007, 9:23 am
Hi,
I've been unable to find a contractor I can afford or am comfortable
with for my bathroom so I decided to "general contractor" it myself.
I'm OK with it taking a long time, but still I have this feeling that
I don't know what I'm getting into. Please let me know if my
sequencing is correct:
1. Demolition
2. Plumbing (drains and rough-in's)
3. Electrical
4. Drywal and wonderboard
5. Wetbed and tile
6. Build curb for frameless shower glass
7. Install vanity and all plumbing fixtures and trim.
8. Prime and paint.
I'm not clear whether I've got 4, 5, and 6 in the right order.
And I appreciate all comments, including telling to forget the whole
project altogether.
Thanks.
Aaron
|