|
Posted by J. Clarke on February 22, 2008, 2:09 pm
raymondjiii@yahoo.com wrote:
>> ransley wrote:
>>
>>
>>>>>> Darn termites!
>>
>>>>>> I need to replace 40' of sill plate from the 7' basement of a
>>>>>> two-
>>>>>> story house. Replacing it from the outside is out of the
>>>>>> question
>>>>>> because of brick veneer and a solid-pour concrete porch.
>>
>>>>>> 28' of the replacement should be fairly straight forward
>>>>>> because
>>>>>> the floor joists are perpindicular to the sill plate. Jack the
>>>>>> house 10' at a time by the floor joists enough to get the old
>>>>>> sill
>>>>>> out then slide in a new PT sill.
>>
>>>>>> The last 12' however will be a PITA.
>>>>>> The floor joists are parallel to the sill plate
>>>>>> There is a floor joist about 4" from the concrete wall limiting
>>>>>> access (maybe removable)
>>>>>> The end joist (above the sill and under the outside wall
>>>>>> framing)
>>>>>> is damaged
>>>>>> The sewer pipe, water line and meter, and gas line and meter
>>>>>> all
>>>>>> are on this 12'
>>>>>> Lots of HVAC ducts here as well to make things fun
>>>>>> And to make it even more fun the building inspector wants
>>>>>> anchor
>>>>>> bolts installed
>>
>>>>>> Any ideas on how to jack/support this 12' span (No its not a
>>>>>> gable
>>>>>> end wall)
>>
>>>>> Where do you have to put in the bolts, in the foundation wall?-
>>>>> Hide quoted text -
>>
>>>> I assume so, this isn't that much of a problem since there are no
>>>> bolts there now and the cinder block is not filled. I could drill
>>>> the
>>>> new sill and install the bolts then fill the holes in the block
>>>> with
>>>> mortar put in the sill and shove the bolts down into the wet
>>>> mortar.
>>>> Tighten them up when it dries. Kind of silly but this is required
>>>> since a new building needs them so a replacement of that part
>>>> (sill)
>>>> requires them.- Hide quoted text -
>>
>>>> - Show quoted text -
>>
>>> To fill the block with mortar it will go to ground level. It
>>> sounds
>>> nuts. Talk to the head inspector there has to be an easier way
>>> that
>>> will pass. I replaced 2, 25 ft 6x6 sills, You wont jack up the
>>> house
>>> with screw jacks and if you have a concrete floor it will be hard
>>> to
>>> not ruin it. My beam was so rotted jacking was not necessary but I
>>> used jacks to hold up the house then I cut down a beam to fit in
>>> place. Bracing to the foundation done right should pass. Get bids
>>> to
>>> get ideas, maybe the inspector is off.
>>
>> Jacking without ruining floor, something to try is a couple of
>> 2x10s
>> under the jack, with an Ipe 1x8 on top of it--the 2x10s distribute
>> the load and the Ipe 1x8 keeps the jack from punching a hole in
>> them,
>> which it would otherwise do if it has any real load on it.
>>
>> At least it worked for me.
>>
>> --
>> --
>> --John
>> to email, dial "usenet" and validate
>> (was jclarke at eye bee em dot net)
>
>
> A jack is going to punch a hole through two 2x10's? I just removed
> the primary steel support column on the bottom floor in the middle
> of
> the house and it did no such thing.
Depends on the 2x10s and the jack I presume. Mine was making good
progress toward going through the first one until I put the piece of
ipe under it.
--
--
--John
to email, dial "usenet" and validate
(was jclarke at eye bee em dot net)
|